SHUTDOWN PROJECT – DRIVE SHAFT REPLACEMENT GEELONG
Over the Christmas/New Year period, Workplace Alliance personnel worked alongside the Boral Waurn Ponds (Geelong) team to come up with a number of innovative solutions to solve a difficult drive shaft replacement strategy that reduced previous change out times from a week to only 3.5 days.
This dramatically improved up time and delivered on overall equipment efficiency.
Well done to the team at Workplace Alliance team led by Phil Bissett, alongside Darren Goulter, Danny Kaucic, Brad Nye, just to name a few.
This project met all KPI’s with no safety issues, no lost time incidents and zero first aid incidents.